DSR Calendar

DSR Calendar

The Daily Site Report calendar gives an overall view of the draft, missing and completed Daily Site Reports and flags missed DSRs as well as provides a way to identify days where a DSR is not created.

Daily site reports can be created and completed from this view.

 

 

 

DSR Calendar

Ensure you are logged into Gate Three.

Navigate to the Daily Site Reports module within the Field Management section of the menu bar and select Daily Site Reports.


  1. Click on the Calendar tab to view the DSR calendar.

  2. Click on the arrows to move from month to month.

A legend is displayed in the view showing the number of completed, draft, and missing Daily Site Reports.

The warning icon displayed on the tab indicates there are missing Daily site reports for specific days highlighted in red.

 

3. Click or hover on a colour coded number within the calendar for more action items or information.

Daily Site Report Status

  • Green represents completed DSR’s. Click on the selected date to view completed DSR’s.

  • Blue represents draft DSR’s. Click on the selected date to view draft DSR’s.

  • Red represents days missing DSR’s. Click on the selected date to create a DSR or to mark the date as No site Activity.

  • Grey represents No activity on site.

 

Calendar Settings

4. Click on the gear icon to access calendar settings.

DSR Dates: Enter a start and end date to view select Daily Site Reports.
Workdays: Check the box to omit weekend activity from the view.
No Site Activity: Enter a date range to view days with no activity.

 

Audit Log

Audit Log provides information on when the document was created (date/time) as well as the document creator. Audit log helps with auditability for submission, approval, and modifications of all documents in Gate Three.

5. Click on the Audit log symbol to access the events log.
6. Click on an event within the audit log for more information.

 

 

 